Energy & Oil Gas
Technofast Addresses Giant Nuts Challenges for Heavy Industries
Heavy industries such as mining, shipbuilding, and power generation have specific requirements for extremely large nut and bolt fasteners.

Heavy industries such as mining, shipbuilding, and power generation have specific requirements for extremely large nut and bolt fasteners. These pose huge difficulties with applying specified bolt tensions because, for example, a nut weighing thirty kilograms will not be tightened with hand tools. Such nuts are installed or removed with sledgehammers, stud heaters, or torque wrenches, which can weigh as much as the person using them. Installation of such large fasteners is extremely time consuming, can be hazardous to workers, and may not result in even tightening of every fastener to the precise tension required for long and safe joint life. Disassembly for maintenance can be equally slow, hazardous, and damaging to equipment and production schedules.

A proven best practice solution is the use of the Technofast EziTite® family of hydraulic fasteners. Assembly and removal times are 15 to 20 times faster than conventional means in structural steel fabrication, and cut downtime while enhancing safety and joint precision. The fasteners are so efficient and swift in operation, including in hazardous, hot, underground, and confined spaces, that they are used in nuclear energy plants where short exposure times to workers are of critical importance. Technofast fasteners are also commonly used in some of the largest and most difficult critical bolting applications in machinery: in electricity generation, steel fabrication in mining, quarrying, materials handling and high temperature processing applications throughout Australasia, SE Asia, and the USA.
“EziTite technology replaces conventional mining and energy methods in situations where time is money, and safety is paramount,” says Technofast Founder and CEO, John Bucknell. Technofast also retains the NQA 1 nuclear manufacturing standard for supply to the Korean Hydro and Nuclear Power (KHNP) organization and supplies operationally critical bolting for their nuclear fueled electricity generating plant. Technofast EziTite was used to tension boiler feed pump bolting at electricity generating plants in South Korea. The application involved 12 large M110 X 4.0 studs, which were 110mm (4.33in) in diameter with an outside diameter of 200mm (7.87in). EziTite® TR High Temperature Hydraulic Nuts were used as an alternative to the former method of large torque wrenches weighing more than 125kg. The Technofast EziTite method resulted in a total installation time of approximately one to two hours, using two personnel, compared with eight hours and three or four personnel using the previous method.
“Large nuts of this diameter can require terrific torque forces to achieve the desired tensioning or require multiple jack bolts on each stud to bring the job within the power range of hand tools for metal work. Really big nuts, such as those widely used in mining (including mining plant and equipment ), energy, and other industries, can easily have 24 jack bolts in total per nut, as did the nuts at the electricity generating plant in Korea,” says Bucknell. “Also, when jack nut fasteners need to be removed, operations staff must untighten the jack bolts in a strict sequence to avoid failure. If they do not, individual jack bolts can break and then the entire assembly would need to be cut off.”
K999 Thailand carries out work of this kind through its pressure vessel fabrication team in Rayong.
Further reading
Follow procurement opportunities across the wider market on Project Atlas Intel.
How K999 can help
Process equipment for energy projects
Pressure containment and pipeline work carries the tightest documentation on the shop floor, and the articles here track the codes and market conditions behind that work.
Pressure vessels and tanks- 01
Pressure vessels, steel tanks and pig launchers built to ASME and client specifications.
- 02
Pipe spool fabrication with heat induction bending for long radius and tight radius bends.
- 03
Full traceability from mill certificates through weld maps to hydrotest records.
More on Energy & Oil Gas
All articlesRequest for quotation
Need fabricated steel to that standard?
Every enquiry is answered within 48 hours by our estimating team in Rayong. The priced quotation follows once drawings, quantities and standards are confirmed. Stainless steel fabrication, structural steel fabrication, pipe spooling, pressure vessels, steel tanks, mining equipment and conveyors, pig launchers, chutes and hoppers, send the package and we will price it.
Before you request a quotation
Steel fabrication quotation questions
What structural steel fabrication, pressure vessel and pipe spooling packages cost, what to send with an enquiry, and how delivery to site works.
Structural steel fabrication is priced from the section and plate tonnage, the detailing and drawing hours, welding and fitting manhours, NDT requirements, blast and coating system, packing and freight. Grade matters as much as weight: AS/NZS, ASTM, JIS and BS sections carry different mill prices, and heavy built up members take longer than rolled sections. Our Rayong workshop produces around 10,000 tonnes of structural steel fabrication a year, so a clear bill of materials is usually enough to price. Send the drawings and we answer within 48 hours; the priced quotation follows once quantities, standards and delivery dates are confirmed.
For steel fabrication work, send the drawings or IFC package, a bill of materials with material grades, the welding and NDT requirements, the coating specification, the delivery port and your site dates. Add the inspection and test plan, any third party inspection requirement, and whether trial assembly or match marking is needed. Where drawings are still in progress, a scope list with sizes, quantities and duty is enough to start, and the estimate is refined once the final package arrives. Every enquiry is answered within 48 hours, and the priced quotation is issued after scope, standards and quantities are confirmed.
Yes. Pressure vessel fabrication is carried out to ASME Section VIII Div. 1 under our ASME U stamp No. 43,462, or to AS/NZS and BS where the project specifies, covering separators, air receivers, water drums, waste heat recovery units and pig launchers. Steel tanks for fuel, biofuel, chemical, water and food duty are designed in house with our E Tank programme to API, ASME, BS and AS/NZS. Because structural steel, vessels, tanks and their supports are built in the same workshops, one enquiry can cover the vessel package, the tank package and the structural steel that carries them, with a single coating and documentation system and one shipment.
Steel fabrication Australia packages are scheduled from a 33,000 m2 Rayong yard with an 80,000 m2 assembly yard inside Sattahip port, so fabrication, trial assembly, blasting, coating and packing run in one place. Programme length depends on tonnage, material lead times, the coating system and inspection scope, and it is confirmed with the quotation. We quote FOB Laem Chabang, Map Ta Phut or Sattahip, or CIF and DAP to your Australian port, with packing lists, weights, lifting points and a data book per shipment. Staged deliveries can follow your site erection sequence instead of shipping everything at once.
There is no fixed minimum. Pipe spooling Australia packages run at up to 3,000 diameter inches per shift on SCH.40, from a single replacement spool to a full plant piping scope, with spools numbered, X rayed where specified and coated to match erection order. Mining equipment fabrication covers chutes, hoppers, ore bins, transfer towers and conveyor structures with Bisalloy, Hardox, rubber lining or hardfacing fitted in house, from one wear liner set to modules of up to 2,500 tonnes assembled at Sattahip. Send the scope list and we will tell you what the smallest sensible batch is for your programme.






